Churchill Road Drainage Upgrade
Public art opportunity
We requested Expressions of Interest (EOIs) from South Australian artists/artist teams to create a public artwork for the Islington Shared Path as part of the Churchill Road Drainage Upgrade.
While this is in progress, we have engaged local artists to paint murals on the abutments of the Regency Road bridge underpass.
A vital investment protecting our community from flood risk.
The Churchill Road Drainage Upgrade (Stage 1) is a critical infrastructure project designed to comprehensively address the long-standing issue of severe and recurring flooding in the low-lying area immediately east of Churchill Road, particularly around Charles Street and Princes Street. This area has been highly vulnerable to flooding, with significant impacts experienced during the devastating floods of 2016.
By constructing a new high-capacity trunk drain connecting Charles Street to the Hindmarsh Enfield Prospect (HEP) channel, this vital first stage will significantly reduce flood risk for over 88 homes. Upon completion of the entire multi-stage Prospect Drainage Scheme Upgrade, 441 properties will be better protected. Beyond flood mitigation, this project will safeguard essential infrastructure like the Australian Rail Track Corporation (ARTC) corridor, support new housing development, and enhance the overall liveability of our city.
This significant $15.6m investment is equally contributed by City of Prospect, the State Government Stormwater Management Authority, and the Federal Government, highlighting the widespread support and importance of this project across all levels of government.
This project aligns with Council's Top 4 Priorities and pillars of Quality Infrastructure and Sustainability as outlined in our 2023-2027 Strategic Community Plan, and our Advocacy Priority of flood mitigation.
See this project come to life
This animation offers a detailed cut-section view of the underground works we'll be undertaking as part of this vital upgrade.
You'll see exactly how the new high-capacity drain will be installed, including where the tunnel boring machine will be used beneath the railway, and get a clearer picture of the broader upgrades that will protect our community from flooding.
Project status and timeline
The construction contract for the remaining sections of Stage 1 has been awarded to Camco (SA) Pty Ltd. The main construction phase is scheduled to commence in November 2025, with the project expected to be completed by September 2026.
Current status:
The new high-capacity trunk drain has been constructed from the HEP channel outlet to the western side of the rail corridor, and from the eastern side of the rail corridor to Devonport Terrace. The work front is currently moving along Devonport Terrace and will then proceed along Churchill Road and into Charles Street.
The Tunnel Boring Machine (TBM) required to construct the new high-capacity trunk drain under the rail corridor has also been launched, and the first of the four ‘drives’ to install the new pipes under the rail corridor has commenced.
Timeline:
Early contractor involvement and advance works, including constructing a crucial section of the trunk drain alongside Renewal SA's Prospect Corner development and the protection and relocation of existing underground services, were completed by Renewal SA's contractor in early 2025.
Service authorities began relocating their existing underground assets to avoid conflict with the new trunk drain.
Essential tree removals in and adjacent to the rail corridor were specifically scheduled for a 72-hour railway shutdown from Friday, June 7 to Sunday, June 9. A qualified fauna handler was on site throughout these works to ensure the safe clearance and relocation of any fauna.
A dedicated community information session was held in July 2025 to provide detailed project information, address concerns, and discuss the ways our contractor will manage the works zone to minimise impacts on the community as much as practicable. Details were announced via direct mail to nearby residents, social media and via this project webpage.
Camco establishes its base on site, and service relocation works are undertaken. This will impact the east-west path links to Churchill Road from the pathway along the rail coridor, however only one path link at a time will be closed so that pedestrians and cyclists can always access the Islington railway station.
A series of new trunk drains will be installed under the rail corridor using a specialised Tunnel Boring Machine (TBM). This method minimises disruption to rail services.
The Tunnel Boring Machine (TBM) required to construct the new high-capacity trunk drain under the rail corridor has been launched, and the first of the four ‘drives’ to install the new pipes under the rail corridor has commenced. The TBM is currently in stand-by mode until the rail corridor improvement works are completed on the October long weekend.
The additional time required for the ground improvement works in the rail corridor has meant that the closure of Pedder Crescent must be extended to early January 2027.
At the same time as the rail crossing tunnelling, Pedder Crescent will be closed to implement conventional 'open trench' drain construction (between the downstream open channel and the western side of the rail corridor).
Construction begins on the eastern side of the rail corridor (Devonport Terrace, Churchill Road, and Charles Street) using 'open trench' methods, requiring potential traffic management, detours, and temporary road closures.
Through collaboration with the rail authorities, the CRDU contractor will undertake ground improvement works in the rail corridor during upcoming planned shutdowns of the freight rail track (late August) and passenger rail network (October long weekend). The ground improvement works will remove any buried foreign objects and tree stumps and backfill with engineered material that is optimal for the operation of the TBM. The TBM is currently in stand-by mode in the area between the freight and passenger rail track and will resume operations after the ground improvement works have been completed.
The additional time required for the ground improvement works in the rail corridor has meant that the closure of Pedder Crescent must be extended to early January 2027.
Constructing the new high-capacity trunk drain Churchill Road will be undertaken in two stages:
- The section of trunk drain that crosses the road will be undertaken as night works. This is expected to take 1 week. On these nights, traffic flows along Churchill Road will be reduced to one lane under ‘stop-go’ traffic control conditions. The night works are required to ensure that traffic flows are returned to normal along Churchill Road during the day.
- The section of trunk drain along the eastern side of Churchill Road, from Devonport Terrace to Charles Street, will be undertaken as day works and one lane of traffic will be maintained in each direction. This is expected to take 3 weeks.
Construction of the new shared use path from the Regency Road bridge underpass to Devonport Terrace (midway between Parnta Avenue and Gurr Street).
The new shared path will include a 3-metre-wide pavement with asphalt surface and line marking, as well as a lighting upgrade and other public amenities such as a shade structure and seating, plus new trees and plantings.
Construction has commenced for the new lighting and pavements for the Islington Shared Use Path. A new pedestrian detour has been established through the Prospect Corner development to enable works to commence on the Northern Shared Use Path.
Access to the Islington Railway Station will remain available at all times.
Project benefits
Once completed, the Churchill Road Drainage Upgrade (Stage 1) will deliver significant benefits to our community:
- Reduced flood risk to over 88 homes immediately, and eventually 441 properties across the entire scheme
- Protection of critical infrastructure, including the Australian Rail Track Corporation (ARTC) corridor
- Improved liveability of the Churchill Road area
- Support for new housing development
- Enhanced community well-being through greater flood resilience.
Additional community benefits
Council has been working closely with Renewal SA and the Department for Infrastructure and Transport (DIT) to fast-track other important community initiatives in the project area. With funding support from Renewal SA, Council will now also be constructing:
- Upgraded connection nodes with feature pavements and seating at three locations along the Islington Shared Use Path
- A new asphalt path and lighting for the Northern Shared Use Path that runs in an east-west direction from the Islington Railway Station to Churchill Road.
DIT has also engaged the CRDU contractor to construct a new disability access ramp to the Islington Railway Station, which was designed as part of Council's Early Contractor Involvement process. Together with the new murals on the abutments of the Regency Road Bridge underpass – this will complete the transformation of the pedestrian and cyclist facilities in this area.
As part of the Churchill Road Drainage Upgrade project, we're also undertaking a design process to improve the Islington Shared Path, next to Islington station. This popular stretch of the Gawler Greenway bike path will receive upgrades to its pavement, lighting, and landscaping to enhance accessibility and usability.
The Islington Shared Path upgrade received a $200,000 contribution from the Department for Infrastructure and Transport's State Bike Fund.
We’re excited to enhance this valuable community asset and make it more accessible and enjoyable for all users.
Latest news
May 2025
April 2025
September 2024
Frequently asked questions
Construction is actively underway. We’ve completed the early contractor involvement and advance works, which included constructing a crucial section of the trunk drain alongside Renewal SA's Prospect Corner development and protecting/relocating existing underground services. The primary construction phase for Stage 1, focusing on the railway crossing and the main trunk drain, began in November 2025 and is expected to be completed by January 2027.
During construction, you’ll see the installation of large concrete pipes (up to 2.1m in diameter) and rectangular box culverts along the proposed drain alignment. This will require the use of large earthmoving equipment, and comprehensive traffic management plans will be in place throughout the construction period to ensure safety and minimise disruption. Once the pipes and culverts are installed, surfaces will be backfilled and reinstated.
In November 2025, our contractor will be establishing their site base on vacant land north of Devonport Terrace. You'll see several work crews simultaneously undertaking "open trench" excavation on local roads (inclduing Devonport Terrace, Churchill Road, Charles Street) and the use of a specialised Tunnel Boring Machine (TBM) for the rail crossing. You can also expect to see the immediate closure of the Islington Shared Path section between Devonport Terrace and Islington Station, and active traffic management, detours, and temporary road closures in the works areas.
The Prospect Drainage Scheme Upgrade is a multi-stage project that will be progressed in four stages:
- Churchill Road Drainage Upgrade (Stage 1)
- HEP Channel Upgrades (Stage 2)
- Churchill Road Drainage Upgrade Extension (Stage 3)
- Prospect Local Roads Drainage Upgrade extension (Stage 4)
The total cost of the Churchill Road Drainage Upgrade project is estimated at $15.6m. This includes equal funding contributions of $5.2m each from City of Prospect, the State Government (via the Stormwater Management Authority), and Federal Government (via the National Emergency Management Agency), reflecting the project’s significance and the shared commitment to addressing flood risk in our community.
Council has allocated a total of $16.1m towards stormwater drainage infrastructure in its Long Term Financial Plan. This includes $5.2m committed to the Churchill Road Drainage Upgrade.
We understand that traffic disruptions can be inconvenient, and we’re committed to minimising impacts on the community.
Traffic management plans will be actively implemented for works in Devonport Terrace, Churchill Road, and Charles Street (see above).
We know the importance of uninterrupted essential services. Council is working closely with service authorities for the successful delivery of this project, including the relocation of some existing underground services to allow the new stormwater trunk drain to be constructed.
While there may be some temporary disruptions to services in specific areas during construction (e.g. water, sewerage, gas), every effort will be made to minimise inconvenience. Advance notifications will be provided to affected residents and businesses prior to any planned disruptions.
Once Stage 1 has been completed, there will be 88 fewer properties affected in a major flood event. By increasing the capacity of the drainage system, we also expect to minimise the impact of future flood events for many more properties and the adjoining transport corridors.
Upon completion of all four stages of the Prospect Drainage Scheme Upgrade, 441 properties will be better protected.
Our contractors will be using a range of equipment necessary for large-scale drainage works, including a tunnel boring machine, excavators, backhoes, graders, rollers, water carts, and various tipper and tandem trucks.
It's possible this project may increase property values in the long term, primarily due to the significant reduction in flood risk and the overall improved liveability in the Churchill Road area. It's also possible that insurance premiums could be reduced for properties that have had a history of flooding, although this is at the discretion of individual insurance providers.
Our contractor undertaking the works is responsible for managing flows in the stormwater system during the construction phase, and the existing stormwater system will remain fully operational throughout construction. The new trunk drain will become operational once it is connected to the existing stormwater system.
Connecting the new trunk drain to the existing system will be undertaken when there is no rain forecast. Contingency plans (such as holding off connection works until rain and subsequent in-pipe water flow stops) will be in place to ensure that the capacity of the existing stormwater system is not adversely impacted if rain occurs unexpectedly. The contractor will also be equipped to manage low flows from small rain events and alternative sources of water flow like car washing or leaking water mains by diverting these low flows around the work site.
Yes, there’ll be opportunities for the community to provide feedback and input into the design of future artworks along the Islington Shared Path. Details on how to participate in this separate process will be communicated as that project progresses.
Contact us
For further information or inquiries, please contact Brett Shuttleworth, Principal Engineer and Project Manager on 8269 5355 or at admin@prospect.sa.gov.au.