Road, kerb, gutter and footpath upgrades
Current and upcoming works
Council’s Kerb Remediation Works Program involves the repairing or renewing of our kerbs to enhance both the quality of our infrastructure and the aesthetics of our community.
Where:
| Location | From | To | Side | When* |
|---|---|---|---|---|
| Pulsford Road | Darmody Street | Main North Road | Both | Mid 2026 |
| Gladstone Road | Braund Road | Prospect Road | Both | Late 2026 |
| Rose Street | Churchill Road | Braund Road | Both | Late 2026 |
| Gloucester Street | Prospect Terrace | Main North Road | Both | Early 2027 |
| Azalea Street/Braund Road Junction | Azalea Street | Braund Road | Junction | Mid 2027 |
| Olive Street pedestrian crossings | Braund Road | Prospect Road | Both | Late 2026 |
| Hepburn Street^ | Jellicoe Street | Brooke Street | Both | TBC |
*Dates are subject to change, dependant on external contractor availability
^Identified as a priority but currently lacks funding
Council’s Footpath Upgrade Program includes replacing aged footpaths, to ensure accessible pedestrian pathways across our city.
Where:
| Location | From | To | Side | When* |
|---|---|---|---|---|
| Devonport Terrace | Gurr Street | Parnta Avenue | East | Late 2026 |
| Gloucester Street | Prospect Terrace | Main North Road | Both | Early 2027 |
*Dates are subject to change, dependant on external contractor availability
Council’s Road Reseal Program aims to enhance community safety, as well as prolonging the life of our local roads.
Where:
| Location | From | To | When* |
|---|---|---|---|
| King Street | Charles Street | Redin Street | Mid 2026 |
| William Street | Albert Street | Redin Street | Mid 2026 |
| Devonport Terrace | Allan Street | Elizabeth Street | Late 2026 |
| Azalea Street / Braund Road intersection | Intersection | Intersection | Mid 2027 |
| Cassie Street | D'Erlanger Avenue | North East Road | Mid 2027 |
| Pulsford Road | Prospect Road | Darmody Street | Late 2026 |
*Dates are subject to change, dependent on external contractor availability
We have a list of all Capital Works projects that have been completed recently.
Project notification procedures
Residents and businesses affected by these projects will receive advanced notification via letter.
Our contractor will provide advice on commencement dates and information about any road closures through another notification letter closer to the construction, as well as a point of contact for any enquiries during the construction works.
We understand that these impacts and closures may result in temporary disruptions and apologise for any inconvenience they may cause.