Draft Churchill Road Stage 3 Streetscape Upgrade

The Churchill Road Master Plan - Stage 3 will take place on Churchill Road between Gurr Street to Livingstone Avenue.

Construction is due to commence in October 2020 and will take six months.

This project involves:

  • Moving forward to the final stage of the Churchill Road Streetscape Upgrade (Stage 3 out of 3). The initial concept design has already been completed and detailed design is underway.
  • New paved footpaths, kerb and gutter, stormwater management, indented parking & bus bays, pedestrian refuges, continuation of bike lane, and tree & vegetation planting.

Members of the community were invited to have their say for the completion of Stage 3, with feedback now closed. That feedback will be used to inform the final design and layout of the Churchill Road Streetscape Upgrade (Stage 3 of 3).

Community feedback and the final design will be discussed at Council's ordinary meeting Tuesday 23 June 2020.

Click here to find out more about this project.